NORTHEAST, Wis. (WBAY) – The Wisconsin Department of Transportation Northeast Region has released its weekly construction update covering active state highway projects and traffic impacts for the week of Aug. 3–7.
Brown County
I-41 Flyover Ramp Improvements
Work on the I-43 northbound to I-41 southbound ramp will consist of completing a polyester polymer concrete overlay on the right half of the ramp through Aug. 7, with minimal operations Friday for Packer Family Night. The ramp remains closed to a continuous single lane through the end of August.
The northbound I-41 on-ramp from WIS 54/Mason Street, closed since July 13, was scheduled to reopen July 31. The related I-41 northbound on-ramp to WIS 29 westbound was also expected to be completed at that time…