The city released an update on the I Street Bridge Replacement Project, noting higher-than-expected costs for delays but reaffirming it as a top priority, with construction now expected to begin in 2027. Photo courtesy of City of Sacramento
SACRAMENTO, CA (MPG) – Construction bids for the I Street Bridge Replacement Project came in significantly higher than expected last week, prompting city officials to reassess costs and next steps for the long-planned project.
The city received proposals from three nationally recognized contractors, with bids ranging from about $398 million to $517 million. Construction of the new bridge was estimated to cost $300 million…