Roundabout construction delayed again due to utility relocation issues

LUCAS COUNTY, Ohio (WTVG) – Roundabout construction at the intersection of Monclova and Albon roads has been pushed back again, now scheduled for June 22. The project is set to be completed in 45 days.

The project was originally supposed to start at the beginning of April. Lucas County Engineer Mike Pniewski said Toledo Edison has not moved its utilities in a timely manner.

Pniewski said the issue with Toledo Edison has caused financial harm to the county and its contractor due to delay claims and extended general condition costs…

Story continues