NORTHBOROUGH – Additional time may be needed to complete the new Northborough Fire Station.
A request for additional time was submitted by a contractor, which cited a variety of factors, including the soil beneath the site, severe winter weather, and structural steel issues. The town approved funding for the station, located at 61-65 West Main Street, in November 2024.
During the July 22 Fire Station Building Committee meeting, officials said that it is still too early to determine whether an extension is justified. The project team expects to meet with the contractor after reviewing responses from the design team and engineers…