County Line Road reopens after 100 days of construction

Crews are wrapping up construction on a portion of County Line Road from Clarkson Street to the U-Haul business access, reopening the roadway after a 100-day closure.

The project addressed a large dip at Lee Gulch that caused safety concerns for drivers. During heavy rain events, the dip would flood and make travel difficult, according to Project Manager Benjamin Pierce.

To fix the issue, crews raised the road, lengthened an 18-inch pipe underneath and added a pond to filter out the water.

  • Watch the full story in the video player below.

While the full closure is ending and detour signage will be removed Thursday after construction ends around 3:30 p.m., according to Pierce, construction is still ongoing in the work zone. Pierce said there will not be more full closures, but drivers should expect traffic shifts as crews complete paving, curbs, gutters and sidewalks…